Apply Envirorend Base Coat to dry insulation using a notched trowel, ensuring good contact with the insulation surface. Embed the reinforcing mesh into the wet base coat with 100mm overlaps and install stress patches at corners. Reinforce all fixing heads with 100mm x 100mm mesh patches before applying a final 1–2mm slurry coat. The finished base coat should be 3–5mm thick.